Upright Management was engaged by J R Richards Pty Ltd to provide 3 rd Party Consultant services for
the Dubbo Regional Organics Processing Plant Project. Our services included undertaking monthly
inspections throughout the delivery phase of the project and final commissioning inspections to
ensure the project was constructed in accordance with the contract between Dubbo Regional
Council and J R Richards. Upright Management provide monthly reports to both the Principal and
Contractor.
The project included the construction of an Organics Processing Facility that will service the Dubbo
Regional Council and adjoining Council areas and consisted of services upgrades, processing tunnels
and associated technologies, maturation pads, administration building and site works.